Burgos, September 7, 2023.- New trend in the construction market in Europe: “Fixed price construction contracts appear to be going out of fashion”. At least this is what Construction Europe magazine has recently published and I summarize below:
Contractors’ reluctance to take on risk by signing up to fixed price deals is understandable under such circumstances. But that leaves clients and investors with a headache: How can public-private partnerships get value for money in the absence of competition? And how can the public sector deliver projects with certainty around the budget and schedule?
Those are some of the questions that a recent event run by the OECD, an intergovernmental organisation that aims to develop better policies, set out to answer.
It gathered together clients, contractors, and experts in procurement in Paris in May to discuss why there was a loss of appetite for fixed price contracts and if so, what could replace them. Public sector clients offered a mixed picture on the question of whether contractors have become less keen on fixed price contracts.
Marcelle Valkenburg, ECI coordinator, Rijkswaterstaat, which is responsible for the design, construction, maintenance of the main infrastructure facilities in the Netherlands, confirmed that this was happening in the country.
And Bjorn Hasselgren, senior advisor, at the government agency in charge of Sweden’s transport administration, Trafikverket noted that even before supply chain disruption, foreign bidders for major projects have been putting in low bids that have discouraged local, large contractors from bidding.
However, Benoit Dupuis, executive director of the Société de Grand Paris, which is in charge of the €36 billion Grand Paris Express megaproject, reported no low bidder issues in recent major tenders, although that project has only just begun.
The company has also set up an indexing clause within its contracts to take account of rising construction input costs and make space for renegotiations within the contracts, in a bid to mitigate the potential risks for contractors.
Meanwhile, two board members of European International Contractors (EIC) who also took part in the discussion – Philippe Dessoy, general manager, Besix and German Grüniger, group general counsel, Implenia – made the point that it wasn’t so much the form construction contracts take that was causing problems.
Instead, they said, it was the fact that the risk allocation in fixed price contracts has changed. Whereas in the past, construction risk, including adjustments for inflation, in fixed price contracts was distributed more evenly, the burden of risk under certain types of contract, such as FIDIC fixed price contracts, has gradually shifted towards contractors, they argued.
Events like rising inflation, supply chain disruption and high energy costs have brought that situation to a tipping point, where contractors feel that it’s unfair that they should shoulder so much of the burden.
A separate panel at the event explored the potential of adopting early contractor involvement (ECI) contracts, given the apparently declining appetite for fixed price contracts.
Countries like the UK and Australia have led the way on innovative contract models involving partnering, alliancing and early contractor involvement. Event attendees considered the idea of exploring such options, given the current lack of appetite for fixed price contracts among contractors.
A two-step process could involve the procuring authority collaborating with contractor, designer and supplier in the initial design stage, potentially with several bidders developing solutions in parallel. That would precede whittling the bidders down to a winner, with the collaborating consortium entering a fixed-price contract.
But the panellists from Sweden, Norway, the Netherlands and the US warned that such an approach would not be a “silver bullet”.
For a start they would require a highly competent public sector client to engage with the private sector.
The approach to their execution would also need to be the right one and would require experience.
And they argued that collaboration could not be used to replace fixed price contracts across the board, instead recommending a more targeted application, which would require good levels of information to facilitate a more science-based approach.
And as far as investors were concerned, when it came to the prospect of two-step ECI, both Darryl Murphy from Aviva Investment as well as Gregg McClymont from IFM investors welcomed it if it proved able to bring greater value to the project and keep contractors interested.
It warned that existing approaches to selecting procurement strategies lack a systematic, science-based approach to inform the capabilities of the client and the application of a particular delivery model on each package.
It cautioned against making the assumption that risk and uncertainty is the same across different types of major projects, which can lead to reducing the focus of a procurement strategy to the choice of a delivery model, whether design and build (DB), engineering, procurement and construction (EPC), and ECI.
The OECD recommended focussing instead on the question of which risk allocation principle should be applied on what part of the project scope.
Information by Construction Europe
Photo by ECA Today
- How Asia is Redefining the European Business Model
- Management in Times of European Economic Volatility
- People and Processes: Building Execution Capacity in 2025
- Multinationals at a Policy Crossroads: Operating Models Under Monetary Easing, Trade Frictions and AI Rules
- Addressing People and Processes in Multinational Management
- Showcasing Leadership Culture in a Multinational Environment
- The New Value of Talent: More Human, More Technical Leadership
- Leading in Times of Uncertainty: Vision and Data
- Summary of the Document: PwC’s 28th Annual Global CEO Survey
- Effective Strategies for Managing Workplace Conflict
- What Is Agentic AI, and How Will It Change Work?
- MIT: Keys for Managers during 2025
- “…carbon-free cement and a significant reduction in emissions”
- DANA: Damage to infrastructure in Valencia, the third most populated city in Spain
- 7 keys to making our companies more sustainable

Leave a comment